SMC seeks moving cashless toll collection deadline to Feb

SMC seeks moving cashless toll collection deadline to Feb

Dec. 1 | San Miguel Corp. is requesting for a February extension of the December 1 deadline for mandatory cashless transaction on expressways There has been a surge in last-minute applications for RFID stickers, SMC president Ramon Ang said SMC also eyes...

DOLE stops work on Skyway Extension pending probe

DOLE stops work on Skyway Extension pending probe

Nov. 24 | The labor department has ordered a stop to all construction activities on the Skyway Extension Project following the weekend accident that killed a motorist and injured at least six others Project contractors and subcontractors also ordered to attend...

SMC to establish 100 more RFID installation sites

SMC to establish 100 more RFID installation sites

Nov. 23 | San Miguel Corp. (SMC) is installing a hundred additional installation sites for motorists wanting to avail of free radio frequency identification (RFID) stickers Motorists can still avail of free RFID stickers even after the December 1 implementation...

SMC eyes support rail, road network for Bulacan airport

SMC eyes support rail, road network for Bulacan airport

Nov. 18 | San Miguel Corp. (SMC) unveiled rail and road network projects that will provide seamless travel to its P740-billion airport project in Bulacan Projects include an 8-kilometer airport toll road connecting the airport to NLEX and Skyway Stage 3, as...

P20B raised from SMC share sale to fund airport, rail projects

P20B raised from SMC share sale to fund airport, rail projects

Oct. 30 | P20 billion raised by San Miguel Corp. will mainly be for investments in New Manila International Airport (NMIA) and Mass Rail Transit 7 (MRT-7) projects P736-billion NMIA in Bulakan, Bulacan capable of accommodating up to 200 million passengers per...

Skyway Extension northbound section done by Dec

Skyway Extension northbound section done by Dec

Oct. 30 | Skyway Extension’s northbound segment is now 70% finished and on schedule for completion by December Once Skyway Extension and Skyway 3 are both complete, travel from North Luzon Expressway to South Luzon Expressway, and vice versa, will just take...

Skyway Stage 3 set for Dec ‘soft opening’, toll free for a month

Skyway Stage 3 set for Dec ‘soft opening’, toll free for a month

Oct. 21 | Skyway Stage 3 connects SLEX with NLEX, serving as alternative to EDSA, with eight access points traversing Makati, Manila, San Juan, and Quezon City. Free use of whole length of expressway from Buendia to North Luzon Expressway. Travel time from...

Skyway Stage 3 linking NLEX and SLEX now complete

Skyway Stage 3 linking NLEX and SLEX now complete

Oct. 13 | A portion of the newly-completed Skyway Stage 3 | Photo from San Miguel Corp. The entire 17.93-kilometer (km) stretch of the Skyway Stage 3 project, which links North Luzon Expressway (NLEX) and South Luzon Expressway (SLEX), is finally complete, but...

Northbound section of Skyway Extension done by Dec

Northbound section of Skyway Extension done by Dec

Aug. 25 | Screengrab of the Skyway Extension project phase 1 video from San Miguel Corp. San Miguel Corp. (SMC) said it expects to finish construction of the northbound section of the P10-billion Skyway Extension project by December. Construction of the northbound...

Fire to extend Skyway Stage 3 completion by 3 months

Fire to extend Skyway Stage 3 completion by 3 months

Feb. 4 | The completion target for Skyway Stage 3 project has been moved by three more months to July 2020 following the collapse of a portion of the road project when a fire razed a nearby warehouse in Pandacan, Manila. “We are saddened by this unfortunate...