NLEX Connector España section completed in Q1 2022

0
861
NLEX Corporation is using the Indonesian technology called Sosrobahu in launching coping beams or pierheads in certain portions of NLEX Connector as this rotating device enables construction of expressways above existing roads with minimum disturbance to traffic. Photo from nlex.com.ph.
  • First 5km section of NLEX Connector will be finished in the first quarter of 2022
  • The next 3km elevated section between España Interchange and the vicinity of the Polytechnic University of the Philippines in Sta. Mesa, Manila will commence construction within the year
  • Once fully complete, the NLEX Connector is expected to serve 35,000 motorists daily and provide better access to Manila Ports and airports such as NAIA and Clark

The first five-kilometer section of NLEX Connector will be completed in the first quarter of 2022 with construction almost halfway done, NLEX Corporation said in a statement.

“The first section of NLEX Connector from Caloocan Interchange to España Boulevard is nearly halfway done,” said Public Works Secretary Mark A. Villar during the inspection of the project’s Manila segment, adding “we are targeting to deliver the full right-of-way (ROW) for this section by next month so we can further accelerate the project.”

For his part, NLEX Corporation president and general manager J. Luigi L. Bautista said, “We are pleased that the construction activities are moving forward with the construction progress standing at 45 percent. Thanks to our government partner, DPWH (Department of Public Works and Highways), for securing the ROW requirements.”

NLEX has allotted P23 billion for the public-private partnership project between Metro Pacific Tollways led-NLEX Corporation and the DPWH.

As the first section of NLEX Connector is being built inside the Philippine National Railways (PNR) ROW and passes through urbanized areas between Harbor Link-Caloocan Interchange along C3 Road/5th Ave. and España Blvd. in Sampaloc, Manila, the tollway company continues to tap technology to accelerate the construction.

The company said it is using the Indonesian technology called Sosrobahu in launching coping beams or pierheads in certain portions of the NLEX Connector as this rotating device enables construction of expressways above existing roads with minimum disturbance to traffic.

“This technology is highly beneficial since it will ramp up the construction progress and most importantly minimize traffic jams thus reduce economic losses. Despite the challenges posed by the ongoing pandemic, we can expect significant progress in the coming months because of this innovative solution,” Bautista said.

Aside from the Sosrobahu, NLEX is using Super T girders to expedite construction for the project that will provide trucks with a 24/7 alternative route and reduce travel time between NLEX and South Luzon from two hours to just 20 minutes.

Super T girders are innovative, pre-stressed box girders that are widely used for bridges in Australia and New Zealand. More than 1,400 girders will be used for the entire project.

NLEX is also utilizing the PNR railway tracks in transporting major structural components from one site to another as part of efforts to speed up construction.

While the NLEX Connector España Section is progressing, the next three-km elevated section between España Interchange and the vicinity of the Polytechnic University of the Philippines in Sta. Mesa, Manila is seen to commence construction within the year.

Once completed, the NLEX Connector will have four toll plazas and interchanges in C3 and España. It is expected to serve 35,000 motorists daily and provide better access to Manila Ports and airports such as NAIA and Clark. This will also enable faster transport of goods and services between Metro Manila and Luzon provinces.